Work Outlook
Boilermakers Local 105
The jobs below are subject to change and will be updated as soon as possible when we receive new information.
Last updated
08/11/2025
Gavin Power Plant
-Enerfab – 8 to 10 weeks. Starting around the end of September to first of October for around 200 boilermakers.
Kyger Creek Power Plant
-Enerfab – Starting around first of September. Starting hiring on September 10th. Working 6-10’s. Outage supposed to last until October 25th. Could get 7 weeks from start of outage to end of outage.
Make sure you have the local selected on the BDS before calling them about work.